MTP Connector Types: Male vs Female, Polarity Explained

- Jan 29, 2026-

MTP Connector Types: Male vs Female, Polarity Explained

Got a call from a customer in Austin last quarter, their integrator had installed 90-something MTP trunks and nothing was working right. Half the 100G links showed errors, the other half would not even come up. Turned out the SI ordered Type A cables for a Method B design, and somewhere along the way the adapter keying got mixed up too. Classic mess. The original cable vendor said specs were followed, SI said they ordered what the consultant spec'd, consultant had already moved on to another project. Customer ended up eating most of the cost because nobody could prove who screwed up first.

 

I am not telling this story to bash anyone. This kind of thing happens more than people admit. MTP has maybe 30-40 different configuration combinations when you factor in gender, polarity type, fiber count, and key orientation. Miss one parameter and you are chasing phantom issues for days.

 

Gender: Pins In, Pins Out, That Is Basically It

 

Male MTP has two guide pins. Female does not. The pins provide mechanical alignment so the 12 or 24 fiber cores actually line up when you mate two connectors.

What matters for your BOM:

Transceivers are male. Cisco, Arista, Juniper, the white-label stuff from China, whatever. Module vendors standardized on pinned ports because pins are protected inside the transceiver cage. So your equipment-side patch cables need female connectors facing the switch.

 

Trunk cables between cabinets are typically male both ends. They plug into adapter panels which are female-to-female. The adapter receives pins from both directions.

 

Cassette modules have female MTP ports on the trunk side. They receive the male trunk end.

Simple chain: male transceiver → female patch cable → male trunk → female adapter → male trunk → female cassette. Get one link wrong and you have a problem.

The nasty failure mode is female-to-female mating when you expected male-to-female. Connectors physically click together. You might even see light on your power meter because fibers are close enough to couple some signal. But without guide pins doing precision alignment, insertion loss goes from 0.25-0.35dB typical to over 1dB. Sometimes 1.5dB or worse depending on how bad the angular misalignment is. On a multi-hop spine-leaf topology that eats your entire link budget before you even get to the far end.

 

 

We had a situation maybe 18 months ago, customer's storage vendor was screaming about latency spikes. Customer blamed the new Arista switches, Arista blamed the SAN, SAN vendor blamed the cabling contractor. Two weeks of finger-pointing. Finally someone thought to scope the MTP end faces and found the contractor had used unpinned jumpers everywhere to save cost. Saved maybe $500 on the fiber bill, cost probably $40K in engineering time across three vendors. And the storage vendor still thinks it was a switch problem.

 

Polarity: Just Use Method B

 

I know TIA-568 defines three methods. Here is the practical reality:

 

  • Method B with Type B cables.That is what you want for 40G/100G/400G parallel optics. Type B flips the fiber array end-to-end, position 1 connects to position 12, Tx lands on Rx automatically. Key-up-to-key-up adapters. Done.
     
  • Method A exists for legacy compatibility.If you have old 10G infrastructure with duplex breakouts and you need new 40G switches to play nice with existing cabling, Method A lets you handle the polarity flip at the patch cord level instead of in the trunk. But then you need to track which patch cords are A-to-A versus A-to-B, and in a big deployment that becomes a labeling nightmare. We have seen customers with 2000+ patch cords lose track within six months.
     
  • Method C flips adjacent pairs instead of the whole array.I genuinely do not know why anyone would choose this for new construction. We maybe sell 10-15 Type C cables a year and it is always for some weird legacy integration.

One thing worth mentioning because it bit a few customers: some older Cisco Nexus 9300 series from 2017-2018 era had different pinout expectations out of the box. If you are mixing that generation Nexus with newer Arista or Juniper gear, do not assume Method B just works. Verify transceiver pinout first. We have a compatibility note on this, ask if you are dealing with mixed-generation Cisco stuff.

Our standing recommendation: Method B trunks, Type A cassettes for LC breakout, A-to-B duplex patch cords at equipment. Have not had a polarity issue on any project using this combination since we standardized on it in 2021.

 

Pre-Terminated vs Field Splice: The Math

 

Pre-terminated MTP costs more per cable. Nobody disputes this. Whether it costs more per project depends on your labor situation.

 

Based on projects we supported in Northeast region over the past 18 months or so:

 

Pre-terminated trunk installation runs 5-8 minutes per cable end. Unbox, route, dress into tray, connect to adapter, visual verify. Faster if your rack layout is clean, slower if you are working around existing cable plant.

 

Field fusion splice runs 18-30 minutes per splice point with certified techs using Fujikura or Sumitomo machines. We have seen 40+ minutes with less experienced crews or cheap equipment, plus rework rates around 15-20% in those cases.

 

On a deployment around 1000 fibers, call it 80-something MTP-12 trunks, you are looking at maybe 15-20 labor hours for pre-terminated versus 60-80 hours for field splice. At $75-100/hour fully burdened (depending on region and union situation), the labor delta more than covers the cable price premium for most project sizes.

 

Where field termination wins: very long runs where shipping assembled cables is awkward, retrofit jobs where you cannot nail down exact lengths until you are on site, or situations where you have fusion capability in-house and labor is basically free. For greenfield data center builds with known pathway lengths, pre-terminated is almost always cheaper total cost.

 

I am not going to pretend our pre-terminated cables are magically better than doing it in the field. The real advantage is factory environment: climate controlled, clean room conditions, 100% tested before ship. Field conditions are unpredictable. I have seen splice trucks set up in parking garages, loading docks, unfinished mechanical rooms with concrete dust everywhere. The fiber does not care about your project schedule.

 

Fiber Count: 12 vs 24, Maybe 16 Later

 

MTP-12

Is the standard for 40G and 100G because QSFP uses 8 fibers. You get 8 active plus 4 dark for future use or management.

MTP-24

Supports 200G (2x 100G over one connector) or 400G-SR8 which uses 16 fibers. Also gives you room for 800G migration later.

If you are building infrastructure today and budget is tight, MTP-12 works fine for 100G. The ecosystem is mature, every vendor supports it, you will not have compatibility surprises.

 

If you have budget flexibility and expect 400G within 2-3 years, go MTP-24 now. Premium is roughly 35-45% over equivalent MTP-12 depending on length and quality tier. Pulling new trunk cables later costs way more than that premium when you factor in downtime coordination and pathway congestion.

 

800G is where it gets complicated. IEEE 802.3df spec uses 8 lanes per direction, so MTP-16 is becoming the connector of choice for 800G-SR8 and DR8. MTP-16 ferrule is different from MTP-12, they do not mate. If you are planning AI/ML infrastructure with 5+ year horizon, this is a real consideration. We have a technical note on 800G migration paths, but honestly the industry is still figuring this out. I would not commit to major infrastructure decisions based on 800G assumptions until transceiver pricing stabilizes, probably late 2025 earliest.

 

What Your PO Needs

 

We catch spec errors on maybe 1 in 6 or 7 orders during review. These are the fields that cause problems:

Fiber count.
Match your transceiver. QSFP28 SR4 is 8 fibers, QSFP-DD SR8 is 16. Ordering 24-fiber cable for SR4 application wastes money.

Gender each end.
Write it out: "A-end Male, B-end Female" or whatever. If PO just says "MTP both ends" we have to call and that adds a day minimum.

Polarity type.
A, B, or C. Must match your adapter keying and overall method.

Polish type.
PC for multimode, APC for singlemode with high return loss requirement. Do not mix them, ever. APC angle mated to PC flat damages both end faces permanently.

Length.
Pre-terminated cables have no field adjustment. If you need 23.7 meters, order 24 meters and plan for a little slack. Or specify tighter tolerance but expect longer lead time.

We have a PO template that forces you to fill in each field. Cuts clarification calls by probably 80%. Email us if you want it.

 

On incoming inspection: ask your vendor for per-cable test data, not batch sample. Quality variation shows up in insertion loss consistency. Elite grade spec is 0.35dB max but if 30% of your cables are sitting at 0.30-0.35dB you have less margin than you think. We ship test reports with every order, the good vendors all do this.

 

When It Does Not Work

 

If links are not coming up and you suspect MTP problems:

 

  1. First, visual check. Male has pins, female has holes. If you see two female connectors mated through an adapter, there is your answer.
     
  2. Second, check key orientation at adapters. Method B should be key-up to key-up both sides. One up and one down means your polarity is flipped.
     
  3. Third, scope the end faces. MTP ferrules are larger than LC, they collect contamination faster. One dirty fiber out of 12 can raise aggregate loss enough to cause problems on 100G.
     

If you call us with an issue, have ready: cable part numbers, what is connected to what, adapter type, and any test readings you have. We can usually figure out configuration errors in one conversation if we have that information.
 

Bottom Line

 

Male mates with female, equipment ports are male, trunk cables are typically male-to-male into female adapters. Method B for parallel optics unless you have legacy compatibility issues. Specify everything explicitly on your PO because suppliers will not guess correctly.

 

If you have a project in spec phase and want someone to sanity-check your BOM, send it over. We do pre-sales review, takes maybe a day depending on complexity, no charge. Easier to catch errors before production than after.